Crews have completed about 60% of the demolition and excavation work at the RUH parkade. A portion of the RUH parkade is being torn down to make way for the new maternal and children’s hospital. This week crews have “chewed” away most of the area surrounding the Cameco Skywalk. The skywalk is expected to be dismantled and demolished by the end of July. Crews will also begin demolishing the parkade structure that is directly adjacent to the 1978 building of Royal University Hospital within the next two weeks.

More pictures of the demolition activity, and the site construction camera, can be found at www.saskatoonhealthregion.ca/chs.

Follow the hospital on Twitter @childrenhospSK or “Like” us on Facebook www.facebook.com/childrenhospSK to stay up to date.

 